Downer Original Helping Hand Framing Solutions are one of the first rainscreen framing systems on the UK market. BBA approved,

Contact

5 Wainwright Close, Churchfields Industrial Estate, Saint Leonards-on-Sea, East Sussex TN38 9PP

Email Us @downerframing.com
Tel: +44(0)1424 852 641


Warning: Trying to access array offset on value of type bool in /homepages/16/d427804638/htdocs/clickandbuilds/Downer/wp-content/themes/allston/vc-templates/vc_row.php on line 179

DCS041
Floor Spanning

DCS041 SYSTEM OVERVIEW

Downer DCS041 floor to floor framing system is designed to provide vertical support to most rainscreen cladding panels using the principle of a ventilated façade with the ability to span over non-load bearing walls and be fixed back to floor slabs.

Wall brackets combined with extruded aluminium box and “T” box profiles provide the installer with an adjustable system allowing for thermal and structural movement and variation in cavity depth to suit project specific requirements.

DCS041 vertical rails offer direct support to the cladding panels by face or adhesive fixing them.

It can also be used as a support to other framing systems such us our DCS004 Mechanical Secret Fix or DCS021 Omega and Zeds for horizontal support.

1. Primary Structure
(Concrete, Masonry, SFS or timber)

2. Insulation

3. DCS041 Isolator Pad

4. Primary Fixing
(varies dependent on Primary Structure)

5. DCS041 Wall Bracket

6. HBS 100×75 A2 S/S Bolt Set

7. DCS041 Box Rail
(box or “T” box available as 6m lengths)

8. 200mm Rail Connecting Spigot

9. FDS 65530 W16 Spigot Retaining Screw

Please note, all illustrations included in this website are representations of the system and structural design analysis must be sought on a project basis.

DCS041 Wall Brackets / Cavity Range

DCS041 wall brackets are available as standard with 30xØ13mm slots (central or side located) to suit most masonry / concrete anchors and in different sizes ranging from 83 to 153mm projection.

DCS041 – WALL BRACKET CENTRE FIXING

DCS041 – WALL BRACKET SIDE FIXING

Framing Zone - Range (R)

downer-dcs041-overview-ranger

Add 5mm to include – Thermal Isolator Pad

DCS041 Rails

Vertical Rails and DCS041 Wall Brackets should be set out in accordance with the structural engineers’ calculations or necessary building regulation.

T box sections generally provide vertical support at panel joint and Box rail sections provide vertical support for intermediate fixing and corner/reveal support. T Box and Box rails are generally supplied in 6.0metre lengths.

Rainscreen cladding fixings should be positioned close to the centre line of the front face of the box rail / legs of T box.

There must be a minimum 10mm gap between the ends of adjacent rails to allow for expansion and cladding panels should never be fixed to two adjacent rails across the expansion gap.

Do not secure the upper and lower rails using the same wall bracket.

DCS041 Helping Hand bracket Isolator pads must be used when there is risk of bimetallic corrosion or thermal bridging and to isolate the bracket from cementitious surfaces.

For ease of lining and levelling rails start from a predetermined datum line corner/opening or return.

The DCS041 system is designed to span between structural floor slabs, so all the supporting wall brackets are fitted to slab edges.

Extruded Alloy Grade 6005A T6

Site Checklist

Before commencing installation of DCS041 framing system please make sure you have received the following information:

  • DCS041 structural calculations* for project specific dynamic and dead loads.
  • DCS041 Wall brackets and rails set out drawings* showing location of dead load (fix point), wind restraint / expansion brackets (sliding point) and box rails horizontal spacing & joints.

Fixed point bracket

Box rails secured using HBS 100x75mm Bolt Set through hole.

Sliding point bracket

Box rails secured using HBS 100x75mm Bolt Set through slot.

Design Considerations

Vertical Rails and DCS041 Wall Brackets should be set out in accordance with the structural engineers’ calculations or necessary building regulation.

T box sections generally provide vertical support at panel joint and Box rail sections provide vertical support for intermediate fixing and corner/reveal support. T Box and Box rails are generally supplied in 6.0metre lengths.

Rainscreen cladding fixings should be positioned close to the centre line of the front face of the box rail / legs of T box.

There must be a minimum 10mm gap between the ends of adjacent rails to allow for expansion and cladding panels should never be fixed to two adjacent rails across the expansion gap.

Do not secure the upper and lower rails using the same wall bracket.

DCS041 Helping Hand bracket Isolator pads must be used when there is risk of bimetallic corrosion or thermal bridging and to isolate the bracket from cementitious surfaces.

For ease of lining and levelling rails start from a predetermined datum line corner/opening or return.

The DCS041 system is designed to span between structural floor slabs, so all the supporting wall brackets are fitted to slab edges.

Approvals

Downer DCS041 system has been BBA approved under certificate no. 20/5792.

Installation Procedure

1. Mark up location of DCS041 wall brackets ensuring that fixed and sliding points wall brackets are positioned correctly.

2. Install DCS041 wall brackets with isolator pads positioned between the rear of the brackets and the building substrate. Use the appropriate primary anchors as dictated by project specific static calculations.

Fixed points (carrying dead load) for both the T Box and Box rails are located at the top of each rail and the sliding points are at the bottom if rails spanning over two floors.

3. If mineral wool insulation is to be fitted ensure that once this is in place access is available to attach the T box and Box rails to the wall brackets.

4. Insert vertical box rails into the DCS041 wall brackets, adjust, check line and level and secure each rail by drilling an 11mm diameter hole through the fix point hole or sliding point slot.

Vertical box rails should always engage a minimum of 30mm into the wall bracket.

5. Fit the M10 x 75mm SS Rail Bolt/Washers/Locknuts to each hole, torque load and secure.

6. Each T Box/Box Rail is jointed at the slab edges by inserting a 200mm long Connecting Spigot into the rear chamber of each rail. Then, fix a single FDS65530 W 16 x 30mm TEK screw approx. 25mm above the joint, centrally to the box spigot.

7. Continue installation of rails following the same procedure as above to complete the sub grid.

8. Proceed with the installation of the remainder of the rainscreen system.

9. When completed and before commencing cladding panel installation, final checks should be carried out on:

a. Level and plumb of vertical rail
b. Correct location of fix and sliding point wall brackets and spigot.
c. Correct torque load applied to primary anchors as recommended by fixing manufacturer.

10. Proceed with cladding panel installation following cladding manufacturer guidelines.

Delivery and Packaging

Most deliveries are made by standard courier unless specific vehicles are requested (For 6m lengths a rigid sided or larger lorry may be required). All products leaving our works are packed in a manner to ensure safe delivery to site. This entails protection by shrink-wrapping and strapping, and with delivery on suitably sized pallets, frames, crates, bundles, or boxes. These normally contain a maximum of 1200kg for pallets and 35kg for non-palletised items for safe handling on site. It should be noted that it is the customers’ responsibility to ensure safe unloading of delivery vehicles.

Vertical box rails should always engage a minimum of 30mm into the wall bracket.

Site Handling

Components must be handled with care in order not to cause loss or damage. Should it be necessary to store the material on site for any length of time, it should be protected from the elements and the environment. A suitable storage area will need to be set aside, storage should be as near as practicable to the areas of working in order to minimise handling, damage and waste.

Maintenance Instructions

Aluminium profiles and façade accessories subjected to normal circumstances and proper cleaning and maintenance, are guaranteed a long-life span in excess of 35 years as stated in Downer BBA certificate 20/5792 Contamination by concrete, mortar, cement and such, is extremely harmful and needs to be rinsed immediately with pure water.

CONTACT US

Please contact using the details below or by using the form opposite.

Downer Framing
5 Wainwright Close
Churchfields Industrial Estate
Saint Leonards-on-Sea
East Sussex
TN38 9PP

Tel: +44(0)1424 852 641

Email: info@downerframing.com